The table below provides the status of DSA projects received by the CGS within the past year.
Status definitions:
-
“Received” designates projects that are in the bin,
waiting for available staff. We anticipate you will receive our review comments within about 8 weeks of the Status Date.
-
“Assigned” designates projects that are
in active review by CGS geologists and/or geotechnical engineers. This category includes “backcheck reviews” in active review at CGS. We anticipate you will receive our review comments within 2 to 3 weeks of the Status Date. Though complicated projects, or projects that require geotechnical engineer review, may require some additional time.
-
“Commented” designates projects where CGS has completed a review, and for which
we are waiting on some type of response from the project team.
-
“Completed” designates projects that have been found
acceptable at CGS, and we do not expect further review.
Web page by: