Para Español
Plug and Abandonment
Subscribe to the Oil & Gas Outreach listserv to receive updates for public meetings and other announcements.
2025 Updates
Project PLUG Work Updates: AllenCo
August 1, 2025: To date, the Department of Conservation (DOC) and contractor, Driltek has plugged 11 of the 21 “Saint James” drill site wells. Other wells have had some partial abandonment completed, but these wells are still undergoing observation before completing those abandonments. The project is expected to be completed by second quarter of 2026 calendar year.
2024 Updates
Project PLUG Work Updates: AllenCo
December 12, 2024: Starting in late December 2024, the Department of Conservation (DOC) and contractor, Driltek, will permanently close 20 oil and gas wells at the Allen Co Energy "Saint James" drill site in Los Angeles. This plan provides community members with essential information about work schedules, safety measures, and emergency contacts. After completion, all oil and gas operation hazards will be removed from the site.
October 7, 2024:The Department of Conservation held a public Zoom/In-Person hybrid meeting on the work to permanently plug and seal oil wells at the AllenCo site.
January 16, 2024
Work to permanently plug two of the 21 wells at the AllenCo Energy, Inc. oil drilling facility located at 814 W. 23rd Street in the University Park neighborhood of Los Angeles began under an emergency authorization issued by the California Geologic Energy Management Division (CalGEM). CalGEM is conducting this work in response to rising pressure in two wells on the site. Work on the two wells is expected to be completed by early February 2024.
Driltek, the contractor for the work, has provided CalGEM with systems to address and reduce any possible impacts related to odor, noise, traffic, transportation, dust, vibration, waste, and emissions. The South Coast Air Quality Management District has approved permits for closed emission control systems that significantly reduce harmful emissions from the well plugging work and diesel engines.
If everything in the contracting and permitting process goes smoothly, CalGEM will strive to plug the remaining 19 wells as early as the second quarter (April-June) of 2024. Otherwise, the work will begin as late as the third quarter (July-September) of 2024.
Depressurization Work Updates 2022-2023
November 8, 2023
CalGEM issued an emergency contract in response to rising pressure in two wells on the site. Work on the two wells is expected to be completed by early February 2024.
NOTE: The emergency contract is separate from the March 5, 2020, order to AllenCo Energy, Inc. requiring the operator to plug all of the St. James wells and permanently shut down the wellsite.
January 4, 2023
CalGEM completed its final review of the contractor’s depressurization work on the 21 wells. All depressurization equipment that was brought onsite has been removed and demobilization completed on December 13, 2022. There are no well operations taking place at the AllenCo, St. James drill site.
As of December 7, 2022, the St. James site depressurization work was complete. CalGEM is working to complete its final review of the contractor’s depressurization work and has completed and signed off on 19 wells and 2 wells are still under review.
On November 28, 2022, the LAFD notified CalGEM that all safety concerns related to the fire suppression system were resolved, and CalGEM made a determination that the depressurization work may resume. Depressurization work at the St. James site resumed on November 29, 2022.
On November 3, 2022, the CalGEM contractor’s depressurization work on the St. James site has been paused due to a faulty AllenCo fire suppression system that released water during the early morning hours, flooding the well cellar. The Los Angeles City Fire Department (LAFD) determined there was no fire, just a malfunctioning alarm and sprinkler system.
A hydrocarbon odor was observed during a CalGEM site visit over the weekend on November 5. As a result, CalGEM has asked the contractor to pause work and is working with a separate contractor to safely drain the water in the well cellar.
For the health and safety of all onsite workers and the neighboring community, CalGEM has also determined the fire suppression system must be fully operational and certified by LAFD immediately prior to continuing any depressurization work at the site.
Once the water is removed from the well cellar and the fire suppression system is fully functional and certified by LAFD, the depressurization work will continue.
As of October 31, 2022, Anderson Integrated Services was able to bleed down gas pressure from all 21 oil and gas wells at the site.
Fluid has been pumped into 11 of the 21 wells to hydrostatically balance upward formation pressure, ensuring the wells become safe and stable. Of those 11 wells, CalGEM has determined one well to be successfully depressurized. CalGEM is currently reviewing depressurization work on the other 10 wells. The contractor is concurrently working on depressurization of the remaining 10 wells. Work on the wells continues.
The well depressurization process began this week at the AllenCo Oil Production Facility St. James site.
As of Friday, October 21, Anderson Integrated Services was able to bleed down gas pressure from 19 of the 21 oil and gas wells. After degassing of the wells is completed, one of the first phases of the work, the next step will be to pump fluid into the wells to ensure the wells become safe and stable.
The well depressurization work is scheduled to begin the week of October 17, 2022, at the St. James site. The contractor has begun to move equipment on to the site.
CalGEM does not anticipate any work-related noise, traffic generation, or other significant impact on the surrounding community during depressurization work. The work will mostly be contained within the property boundary. CalGEM has required all on site work to take place between the hours of 8:00 a.m. to 5:00 p.m., Monday through Friday.
On September 26, 2019, CalGEM issued
Order number 1162 to AllenCo Energy, Inc. (AllenCo). AllenCo appealed the order and after a hearing before the Director's Office of Appeals the order was affirmed on January 21, 2020. The Remedial Order requires AllenCo to provide CalGEM with a work plan for safely depressurizing wells and placing a suitable fluid in the wells which would render zero gas pressure at the wellhead. AllenCo has not provided CalGEM with a work plan nor otherwise commenced remedial work pursuant to the Remedial Order.
As a result of the operator’s inaction to fulfill requirements of the Remedial Order, the Department of Conservation Geologic Energy Management Division (CalGEM) made the decision to move forward with depressurization of oil and gas wells at the AllenCo Oil Production Facility.
CalGEM selected Andersen Integrated Services as the contractor for the well depressurization work at the St. James site. The contract has been finalized and executed on August 5, 2022. Necessary planning and preparatory work, including obtaining appropriate permits from the South Coast Air Quality Management District (SCAQMD) to operate the emission control equipment, is underway. CalGEM anticipates the depressurization work to begin in mid-to-late September and may continue through mid-December.
On September 15, 2022, Andersen Integrated conducted preparatory work onsite. This work consisted of fluid level measurements in the wells. CalGEM's Southern District is overseeing the contractor’s work.
Background
The City of Los Angeles filed a civil enforcement action in January, 2014, alleging, in general, that AllenCo Energy Inc. was in violation of California's oil and gas laws, public health and safety laws, air and water quality protection laws, and fire and safety, and odor regulations. The Final Judgment in that case directed AllenCo to provide evidence of compliance with laws and orders, install a continuous air-monitoring system, and obtain approval from the Los Angeles City Attorney before resuming operations.
In its oversight of AllenCo, CalGEM (formerly DOGGR) has routinely inspected the facility to assess it for gas leaks and wellhead pressure in attempt to ensure that the facility is being maintained in a manner that prevents, as far as possible, damage to the health and safety of California’s citizens, or damage to the environment and natural resources.
Since August 2018, an interagency group, including CalGEM, community representatives, and interested stakeholders, led by the Los Angeles County Department of Public Health, has met regularly to report on activity at the facility and inspections.
On March 5, 2020, the State Oil & Gas Supervisor issued a Plug and Abandonment Order to AllenCo Energy, Inc., to permanently close its Saint James drill site in South Central Los Angeles. Among other requirements, the company must plug and abandon (permanently seal) the 21 wells. AllenCo had been seeking approval to restart production after shutting down in late 2013 for numerous violations. Read Order 1174 from the State Oil & Gas Supervisor to AllenCo Energy , Inc. (PDF) for details. Order 1174 was appealed by AllenCo and resolved through a stipulated agreement finding the wells deserted and presumed orphan.
In March 2022, the Los Angeles Superior Court approved CalGEM’s application to access the St. James drill site to perform an inspection and walk through for prospective depressurization-work contractors after CalGEM was unable to acquire access to the site from AllenCo. Representatives from the community were present when public safety officers were there to execute the warrant.
Resources
CalGEM Documents Related to AllenCo Energy Inc.
-
Notice of Violation, leaking wells, to Allenco Energy, Inc. September 18, 2019 (PDF)
-
CalGEM Response to AllenCo Revised Startup Plan, December 24, 2018 (PDF)
-
CalGEM Receipt of AllenCo Revised Startup Plan, October 4, 2018 (PDF)
-
AllenCo Revised Startup Plan to CalGEM, July 5, 2018 (PDF)
-
CalGEM Response to AllenCo Startup Plan, July 5, 2018 (PDF)
-
AllenCo Startup Plan to CalGEM, March 30, 2018 (PDF)
- Order 1047 to Allenco Energy, Inc, April 28, 2014 (PDF)
4 de enero de 2023
CalGEM completó su revisión final del trabajo de despresurización del contratista en los 21 pozos. Todo el equipo de despresurización que se llevó a los sitios ha sido retirado y la desmovilización finalizó el 13 de diciembre de 2022. No se están llevando a cabo operaciones de pozo en el sitio de perforación de AllenCo, St. James.
14 de diciembre de 2022
El 7 de diciembre de 2022 habían concluido los trabajos de despresurización del sitio de St. James. CalGEM está trabajando para completar su revisión final del trabajo de despresurización del contratista y ha completado y autorizado 19 pozos, y 2 pozos están todavía bajo revisión.
1 de diciembre de 2022
El 28 de noviembre de 2022, el Departamento de Bomberos de Los Ángeles (LAFD, por sus siglas en inglés) notificó a CalGEM que se resolvieron todos los problemas de seguridad relacionados con el sistema de supresión de incendios y CalGEM tomó la determinación de que se puede reanudar el trabajo de despresurización. El trabajo de despresurización en el sitio de St. James se reanudó el 29 de noviembre de 2022.
el 9 de noviembre de 2022
El 3 de noviembre de 2022 se detuvo el trabajo de despresurización del contratista de CalGEM en el sitio de St. James, debido a un sistema defectuoso de supresión de incendios de AllenCo, que liberó agua durante las primeras horas de la mañana, inundando el sótano del pozo. El Departamento de Bomberos de la ciudad de Los Ángeles (LAFD, por sus siglas en inglés) determinó que no hubo incendio, solo una alarma y un sistema de rociadores que estaban fuera de servicio.
Se percibió un olor a hidrocarburo durante una visita al sitio de CalGEM durante el fin de semana del 5 de noviembre. Como resultado, CalGEM le ha pedido al contratista que detenga el trabajo y está trabajando con otro contratista para drenar el agua en el sótano del pozo de manera segura.
Para la salud y la seguridad de todos los trabajadores en el sitio y la comunidad vecina, CalGEM también ha determinado que el sistema de extinción de incendios debe estar completamente operativo y certificado por LAFD inmediatamente antes de continuar con cualquier trabajo de despresurización en el sitio.
Una vez que se elimine el agua de la bodega del pozo y el sistema de supresión de incendios esté completamente funcional y certificado por LAFD, continuará el trabajo de despresurización.
1 de noviembre de 2022
A partir del 31 de octubre de 2022, Anderson Integrated Services pudo purgar la presión del gas de los 21 pozos de petróleo y gas del lugar.
Se ha bombeado fluido en 11 de los 21 pozos para equilibrar hidrostáticamente la presión ascendente de la formación, garantizando que los pozos sean seguros y estables. De esos 11 pozos, CalGEM ha determinado que un pozo se despresurizó con éxito. CalGEM está revisando actualmente los trabajos de despresurización de los otros 10 pozos. El contratista está trabajando simultáneamente en la despresurización de los 10 pozos restantes. Los trabajos en los pozos continúan.
Actualización: 21 de octubre de 2022
El proceso de despresurización del pozo comenzó esta semana en el sitio de AllenCo Oil Production Facility de St. James.
A partir del viernes 21 de octubre, Anderson Integrated Services pudo reducir la presión del gas de 19 de los 21 pozos de petróleo y gas. Una vez finalizada la desgasificación de los pozos, una de las primeras fases de los trabajos, el siguiente paso será bombear fluido en los pozos para garantizar su seguridad y estabilidad.
Actualización: 14 de octubre de 2022
Está previsto que los trabajos de despresurización del pozo comiencen la semana del 17 de octubre de 2022 en el sitio de St. James. El contratista ha comenzado a trasladar el equipo a la obra.
CalGEM no prevé ningún ruido relacionado con el trabajo, generación de tráfico u otro impacto significativo en la comunidad circundante durante los trabajos de despresurización. Las obras estarán contenidas en su mayor parte dentro del límite de la propiedad. CalGEM ha requerido que todo el trabajo en el sitio se lleve a cabo entre las 8:00 a.m. y las 5:00 p.m., de lunes a viernes.
Actualización: 28 de septiembre de 2022
El 26 de septiembre de 2019, CalGEM emitió la
Orden número 1162 a AllenCo Energy, Inc. (AllenCo). AllenCo apeló la orden y tras una audiencia ante la Oficina de Apelaciones del Director la orden fue confirmada el 21 de enero de 2020. La Orden de Remediación requiere que AllenCo proporcione a CalGEM un plan de trabajo para despresurizar los pozos de forma segura y colocar un fluido adecuado en los pozos que haga que la presión del gas sea nula en la cabeza del pozo. AllenCo no ha proporcionado a CalGEM un plan de trabajo ni ha comenzado de otro modo los trabajos de reparación de acuerdo con la Orden de Reparación.
Como resultado de la inacción del operador para cumplir con los requisitos de la Orden de Remediación, la División de Gestión de Energía Geológica del Departamento de Conservación (CalGEM) tomó la decisión de seguir adelante con la despresurización de los pozos de petróleo y gas en la Instalación de Producción de Petróleo de AllenCo.
CalGEM seleccionó a Andersen Integrated Services como contratista para el trabajo de despresurización de pozos en el sitio de St. James. El contrato ha sido finalizado y ejecutado el 5 de agosto de 2022. La planificación y los trabajos preparatorios necesarios, incluida la obtención de los permisos adecuados del Distrito de Gestión de la Calidad del Aire de la Costa Sur (SCAQMD) para operar el equipo de control de emisiones, están en marcha. CalGEM prevé que los trabajos de despresurización comiencen a mediados o finales de septiembre y puedan continuar hasta mediados de diciembre.
El 15 de septiembre de 2022, Andersen Integrated realizó trabajos preparatorios en el sitio. Este trabajo consistió en la medición del nivel de fluido en los pozos. El Distrito Sur de CalGEM está supervisando el trabajo del contratista.
Antecedentes
En su supervisión de AllenCo, CalGEM (anteriormente DOGGR) ha inspeccionado rutinariamente la instalación para evaluarla en busca de fugas de gas y presión en la boca del pozo en un intento de garantizar que la instalación se mantenga de una manera que evite, en la medida de lo posible, daños a la salud y seguridad de los ciudadanos de California, o daños al medio ambiente y los recursos naturales.
Desde agosto de 2018, un grupo interinstitucional, que incluye a CalGEM, representantes de la comunidad y partes interesadas, dirigido por el Departamento de Salud Pública del Condado de Los Ángeles, se ha reunido regularmente para informar sobre la actividad en la instalación y las inspecciones.
El 5 de marzo de 2020, el Supervisor Estatal de Petróleo & Gas emitió una Orden de Taponamiento y Abandono a AllenCo Energy, Inc. para que cerrara permanentemente su sitio de perforación de Saint James en el centro sur de Los Ángeles. Entre otros requisitos, la empresa debe tapar y abandonar (sellar permanentemente) los 21 pozos. AllenCo había estado buscando la aprobación para reiniciar la producción después de cerrarla a finales de 2013 por numerosas infracciones. Lea la Orden 1174 del Supervisor Estatal de Petróleo & Gas a AllenCo Energy , Inc. (PDF) para más información. La orden 1174 fue apelada por AllenCo y resuelta mediante acuerdo estipulado encontrando los pozos desiertos y presuntamente huérfanos..
En marzo de 2022, el Tribunal Superior de Los Ángeles aprobó la solicitud de CalGEM para acceder al sitio de perforación de St. James para realizar una inspección y un recorrido para los posibles contratistas de trabajos de despresurización después de que CalGEM no pudiera obtener el acceso al sitio de AllenCo. Representantes de la comunidad estuvieron presentes cuando los oficiales de seguridad pública estaban allí para ejecutar la orden.
Recursos
Documentos de CalGEM relacionados con AllenCo Energy Inc.
-
Notice of Violation, leaking wells, to Allenco Energy, Inc. September 18, 2019 (PDF)
-
CalGEM Response to AllenCo Revised Startup Plan, December 24, 2018 (PDF)
-
CalGEM Receipt of AllenCo Revised Startup Plan, October 4, 2018 (PDF)
-
AllenCo Revised Startup Plan to CalGEM, July 5, 2018 (PDF)
-
CalGEM Response to AllenCo Startup Plan, July 5, 2018 (PDF)
-
AllenCo Startup Plan to CalGEM, March 30, 2018 (PDF)
- Order 1047 to Allenco Energy, Inc, April 28, 2014 (PDF)